How to build a change house made of wood, on a metal frame

Having bought a plot, land, you think about the fact that you need to live somewhere during the construction of the house. Such a temporary dwelling in a summer cottage or garden plot is a change house. A small insulated structure, usually 3 * 6 or so in size. There are many offers on the market: both wood and metal. But their quality is more than doubtful; the cheapest materials are used during construction. It is easy to verify this by calculating the costs that you will incur if you decide to make a change house with your own hands. With the same dimensions, you will most likely not be able to get cheaper, and if there is a saving, then it will be small. You will consider normal materials, not the cheapest. But in terms of quality and strength, homemade cabins are many times superior to purchased ones.

Change house on the site is the first (or second after the toilet) structure that appears on the site

Change house on the site first (or second after toilet) a structure that appears on the site

What and how they build

Almost all cabins are built using frame technology. As building materials for the frame, a wooden beam of at least 100 * 150 mm or a profiled metal pipe 60 * 60 * 2 mm is used.

For cladding, the choice of materials is much wider. Use:

In any case, the cladding is done on both sides - outside and inside. The outer one can be metal, but inside it is often made either clapboard or stuffed with plywood or OSB.

One of the options for a garden shed

One of the options for a garden shed

Thermal insulation is placed between the two skins. Although the structure is temporary, spring and autumn, and sometimes summer nights, can be very cold. Therefore, without insulation - nothing. Any kind of insulation can be done. Better - mineral wool, cheaper - foam. Extruded polystyrene foam has the best characteristics, but also the highest price. Only when choosing a heater, keep in mind that the styrofoam almost does not drown out sounds, so especially nervous ones will not be able to sleep. Therefore, the best choice is mineral wool. Which layer? If by reason, then in Central Russia, preferably 100 mm, but at least 50 mm.

Please note that the floor also needs to be insulated. Especially the floor. The bottom is very pulling. Therefore, it should be double: first, a rough one, on top, across the board, they put logs, insulation between them, and then the final floor.

Layout and drawings

Despite the fact that the building is considered temporary, it often turns into a bathhouse or a guest house. Therefore, even in a change house there is such a thing as a layout. Even temporary housing should be relatively comfortable.

Change house trailer

There are two main types of cabins: trailer and vest. In a building of the "trailer" type, the entrance is on the side, there is no separation inside, in extreme cases they put a partition - 1.5-2 meters from the entrance. This room is used as a changing room and a warehouse for storing tools.This is the simplest possible option.

Drawing of a cabins with dimensions

Drawing of a cabins with dimensions

In the drawings, there will be graphic and digital symbols, their decoding in the photo below.

Designation in drawings

Designation in drawings

Undershirt

The most popular layout is a vest. This is when the entrance is in the middle. and the middle is fenced off and used as a vestibule, storage room, etc. The purpose of the other two rooms may be different. Someone uses both as bedrooms, someone as a kitchen.

Two rooms and a vestibule

Two rooms and a vestibule

With a small fenced-in pantry

With a fenced-in small pantry

Only vestibule without pantry

Only vestibule without pantry

Change house with toilet and shower

Not everyone agrees, even at a construction site or a summer residence, even temporarily, to lead a Spartan lifestyle. At least basic amenities are required. Although, it is probably better to build them separately.

How to build a toilet on the street read here, but how make a summer shower - in this article.

The san block is on the edge - a wiser decision, especially if you make a separate entrance

The san block is on the edge - a wiser decision, especially if you make a separate entrance

Change house with toilet

With toilet

Having chosen a drawing, do not forget, when developing a frame for a change house, that racks must be placed at the junction of the walls. If doors are attached to the racks, they must be reinforced - double.

Foundation for a change house

Since the structure is temporary and lightweight, the foundation is usually pillars or blocks. More often - blocks. Preferably - concrete, standard. No - you can use any construction, but high density and not hollow.

An example of a column for a foundation for a change house

An example of a column for a foundation for a change house

They are placed on a prepared base. If the soils are normal, you can simply remove the sod and level the pads. For greater reliability, a small pit is dug under each block with a depth of about 20-25 cm. Crushed stone of the middle fraction is poured into it and rammed well. Blocks are placed on such a substrate.

Note! The upper edge should be level (in the same horizontal plane). It is also necessary to check the geometry of the foundation: the angles are strictly at 90 °, the diagonals are equal.

With a change house width of not more than 2.5 m and using a wooden beam for the frame, blocks are placed in each corner, as well as under those places where partitions depart. If the building will be without partitions, the spacing - every 1.5-2 m - depends on the section of the timber and the planned sheathing, as well as the weight of the roofing material. With a width of 3 m or more, an intermediate bar is required, and a base for it. In this case, three rows of blocks are obtained.

An example of a foundation for a three-meter wide summer cottage

An example of a foundation for a three-meter wide summer cottage

To prevent dampness from drawing into the premises, waterproofing is laid on the blocks. You can - two layers of roofing material, you can - another waterproofing material, even a film. Another option is to smear it with bituminous mastic. On this, the foundation can be considered ready.

Step by step instructions: photo reports with explanations

It is difficult to understand some things from the description. No matter how much you read, but until you do it, or at least you don’t look at how others are doing, you don’t understand. That is why photos of the construction of change houses are useful: you can consider how the nodes were made and find a solution for yourself. This is a kind of guide for those who decided to build on their own.

Construction of a wooden change house

A change house was built from wood in the country. Dimensions 3 * 6 m, insulated - for temporary residence during the construction of the house. We used the following materials:

  • board 50 * 100 mm - 28 pcs;
  • timber 100 * 150 mm - 5 pieces and 50 * 50 mm - 24 pieces;
  • blocks 20 * 40 * 20 mm - 20 pcs;
  • roof boards 25 * 150 mm - 10 pieces;
  • tongue-and-groove floor board 30 mm thick - 21 pcs;
  • lining class A 5 packs of 6 meters and 6 packs of 3 meters;
  • roofing material 4 rolls;
  • foam plastic - 4 cubes;
  • windows 90 * 90 cm - 2 pcs;
  • doors;
  • Senezh Ultra - 10 l;
  • corners and plates for strengthening the strapping connections;
  • fasteners (nails, screws, finishing nails), polyurethane foam.

    This is what the materials on the site look like

    This is what the materials on the site look like

Since the prices for materials are very dependent on the region, it makes no sense to talk about the cost of construction. But according to this list, you yourself can determine with fairly high accuracy how much a change house built with your own hands will result.

Please note that in this list there is no roofing material (ondulin was planned) and there is no glass. Also not purchased lining for interior decoration.

Before the start of construction, all wood, with the exception of the lining, was treated with Senezh Ultra antibacterial impregnation. Covered in two layers. So the processing quality should be normal.

Wood processing

Wood processing

We marked the site for the building. We decided to put the blocks on a sand bed. They dug holes 25-30 centimeters deep, poured sand, tamped it down. We set up blocks.First they set up the two outermost ones, put an even board on them, and a level on it. This is how the extreme blocks were exposed. Then the intermediate ones were adjusted under the board height. So on all sides.

Exposing blocks

Exposing blocks

Then the harness was laid. Beam 100 * 150, sawn down in half a tree. Folded, for reliability, pulled together with hairpins.

This is how they cut in half a tree

This is how they cut in half a tree

And this is how to lay the middle bar

And this is how to lay the middle bar

Checking the corners and diagonals knocked down with hairpins

Checking the corners and diagonals knocked down with hairpins

The next step was to lay the floor logs. They were placed every 50 cm, after one we will put the racks. Made from a 50 * 100 mm board placed on a narrow part.

We laid the floor logs

We laid the floor logs

We decided to immediately assemble racks on the ground, strengthen the joints with corners, and then install them ready-made. Collected from the same board 50 * 100 mm.

We knock down the front pillar - it is longer, the back and the rafters

We knock down the front pillar - it is longer, the back and the rafters

They beat them with nails, and the plates were screwed on with self-tapping screws

They beat them with nails, and the plates were screwed on with self-tapping screws

The racks were fixed with temporary jibs

The racks were fixed with temporary jibs

They nailed the racks with long nails. Then, for reliability, all attachment points were reinforced with corners and plates. They were already being put on self-tapping screws.

On the sides of the lag, bars of 50 * 50 mm were nailed. It turned out "nests" for styling foam. It was placed on polyurethane foam: both hermetically sealed and secure. A floorboard was nailed from above.

 

Nailed a bar on both sides of the lag

Nailed a bar on both sides of the lag

Laid the foam

Laid the foam

The floor was laid on top

The floor was laid on top

Then the cladding stage began. First, we put additional racks on the sides, reinforced them with jibs.

Additional struts and jibs give greater rigidity to the structure

Additional struts and jibs give greater rigidity to the structure

Now the skin has gone directly. On the short side, lining went from packs of 3 meters, on the long ones they nailed six meters.

Plating start

Plating start

Having made the sheathing up to half, the lathing was laid under the roofing. We nailed a board 25 * 150 mm in 30 cm increments, along the edges a 20 cm step (so that the overhang could withstand). Then they continued the cladding.

In places where the windows will stand, they put mortgages - a board that lies across the rack. The window frame will rest on it. They were fastened with nails, through and through, but additionally the connections were reinforced with corners.

Installed mortgages in places where windows are supposed to be fastened

Installed mortgages in places where windows are supposed to be fastened

When the back and blank side walls were sewn up almost to the top, roofing material was rolled out onto the roof. It will remain until we buy ondulin.

Sheathing continues

Sheathing continues

the outer cladding is almost complete. The doors were bought without finishing - only the frame sheathed with fiberboard

The outer cladding is almost complete. The doors were bought without finishing - only the frame covered with fiberboard

Starting door trim

Starting door trim

While we were finishing nailing the lining on the outside, work was also in full swing inside - they put foam plastic. The width of the sheet is 100 cm, the distance between the posts is 95 cm. We have to cut off thin strips.

We put foam between the racks

We put foam between the racks

So that it does not "fall", we grab it from above with thin corners, which we attach, of course, only to the bar of the rack.

It looks like a room sheathed with foam from the inside

It looks like a room sheathed with foam from the inside

The corners at the top are visible, which hold the foam

The corners at the top are visible, which hold the foam

We started the cladding inside, but the lining ended. While switched to painting outside. It turned out well, it seems.

It looks like a painted change house outside

It looks like a painted change house outside

We bought additional lining, finished interior decoration.

Inside, too, was lined with clapboard

Inside, too, was lined with clapboard

We started making the partition. It was collected from the same boards - 50 * 150 mm. The joints are traditionally reinforced with corners. Sheathed - with clapboard.

Drains under the partition

Drains under the partition

Sheathed on one side with clapboard

Sheathed on one side with clapboard

We started roof insulation. We used the same polystyrene and the same technology - propped up with corners.

Insulation of the shed ceiling

Insulation of the shed ceiling

The joints with wall insulation were foamed with polyurethane foam.

The joint with the wall insulation was propened

The joint with the wall insulation was propened

After they began clapboarding.

The beginning of the ceiling clapboard

The beginning of the ceiling clapboard

Headliner Finished Headlining Finished

Headliner finished

We started laying the roofing. We bought an ondulin and laid it with an overlap on one wave. They were fastened to each wave with special hardware purchased together with ondulin.

Fastening a single rail on the roof of a garden shed

Fastening the ondulin on the roof of the garden shed

Then they began to bring the interior to mind. The partition was also insulated with polystyrene, sheathed with clapboard on the second side.

Almost wired partition

Almost wired partition

Finishing the piece above the doorway

Finishing the piece above the doorway

This is how it looks

This is how the pier looks in the final version.

The lining is covered with water-based varnish inside. It gives only a slight tint in a slightly darker color. It seems like there is no film on wood. If you look directly, then in general it seems that the tree is not covered with anything. It is only when viewed from the side at a certain angle that shine is visible.

This is after painting

This is after painting

On the floor, the varnish is already with a film: so that the wood does not wear out. Covered in two layers.

Then we started finishing the overhangs. They were sewn up with the same clapboard. In general, working with the clapboard took the most time.

We close the roof overhangs

We close the roof overhangs

The front is almost finished

The front is almost finished

And this is a side view

And this is a side view

Metal frame for the change house

The metal was chosen as the base as more reliable and durable. The thought that the change house might have to be dragged also played a role. If the frame is made of metal, nothing threatens it.

We are going to build something like such a change house.

We are going to build something like such a change house.

The dimensions were determined based on the length of the corner whips: 11.7 m. The following dimensions emerged: 2.8 * 5.8 m, height - 2.5 m. The frame is welded from the corner with a shelf of 75 mm, 6 mm thick.

The foundation is made on self-cast pillars: construction began in the fall, and there is still nothing more to be done. So it was decided to fill in reinforced posts: six pieces. First, the site was marked, after which the places for the foundation posts were determined.

Site marking and base for posts

Site marking and base for posts

Pits were dug 50 * 50 cm, total depth about 30 cm. At the bottom, crushed stone was poured with a layer of about 10-15 cm and tamped tightly. There is the same amount of sand on top, also with a rammer. As a result, the bed was flush with the ground.

Roofing material is laid at the bottom so that moisture does not leave the concrete, and it “matured” normally, and not dried out. Next, the formwork was assembled and reinforcement was laid in it.

It looks like a formwork under a post and reinforcement

It looks like a formwork under a post and reinforcement

The plot is dry, the water runs out normally, so there shouldn't be any problems. I just mastered welding, so that the fittings are either welded or twisted is not clear.

Before pouring concrete

Before pouring concrete

Everything is filled with concrete, covered with a film: the end of October, and in order for the concrete to be of normal strength, it must be wrapped up.

The columns are wrapped

The columns are wrapped

The frame of the frame was cooked for a long time - all winter: frosts, workload, did not allow to act with the required frequency. The base was cooked from a corner of 75 mm, 6 mm thick, 40 * 2 mm was allowed for reinforcement.

The beginning of the change house frame from the metal corner - the lower strapping

The beginning of the change house frame from the metal corner - the lower strapping

The side parts were cooked entirely, then, with the help of 4 people, they were placed in an upright position and so fixed. On the racks to which the frames of windows and doors will be attached, profiled pipes 40 * 40 * 2 mm went.

The frames are going to lie down

The frames are going to lie down

The most inconvenient moment is to measure the diagonals alone. You have to control them all the time, but doing it alone is inconvenient. But everything must be set, otherwise there will be a bias.

To give greater rigidity, I welded metal strips in the corners. They received them by loosening the corner (40 mm). It was possible to buy a strip, but I used corner trims.

Rigidity strips

Stiffening strips in frame corners

Inside corner view

Inside corner view

It was difficult when they put the frames: in the cold, only with thick gloves, and it is difficult to hold firmly in them. Therefore, they propped up with boards, with everything possible. But the angle was kept strictly.

The first circuit is exposed

The first circuit is exposed

So that there is a rigid attachment to the frame, metal plates are welded with an angle.

Having exposed the sides of the frame, they were rigidly connected using a metal corner

Having exposed the sides of the frame, they were rigidly connected using a metal corner

The whole frame is gradually assembled.

The sides are raised and welded

The sides are raised and welded

We finish the plates in the corners

We finish the plates in the corners: above and below

We weld several beams at the top. Now the frame for the change house is on the iron

We weld several beams at the top. Now the frame for the change house is "iron"

The frame from the metal corner for the change house is ready

The frame from the metal corner for the change house is ready

Now the skin remains. It can be any: at least the same lining, block house, at least an economy option - plywood and OSB. To attach the bleaching to the corner, it is more convenient to screw the timber, and to it the crate and everything else are already attached.The same situation is for the rafter system: around the perimeter, a bar is screwed onto self-tapping screws with preliminary certification, the rafters are attached to it.

Related Videos





Similar posts
comment 2
  1. Alexander
    04.03.2018 at 11:25 - Reply

    I also decided to build a change house on the site, purchased very poor quality.
    Your site helped to understand the order and the basics of construction. Thank you!

  2. Alekseich
    05/19/2019 at 19:03 - Reply

    To insulate the wall between wooden posts or the roof between the rafters with foam plastic - ensure the rapid decay of these wooden elements: steam coming from the inside accumulates in the wood, since the foam does not let it through.

Add a comment

Heating

Roof

Doors